This the first of our four CAPM practice exams. These questions are designed to help you prepare for your Certified Associate in Project Management (CAPM) certification exam. There are 48 challenging questions on this practice test covering a wide range of topics. It is based on the CAPM Guide 6th Edition. Start your test prep right now with our free CAPM practice exam!
Vielleicht mit zahlreichen Übungen fehlt Ihnen noch die Sicherheit für PMI CAPM Prüfung, Hohe Bestehensrate, Der Grund, warum die meisten Menschen Webapptron CAPM Dumps Deutsch wählen, liegt darin, dass Webapptron CAPM Dumps Deutsch ein riesiges IT-Elite Team hat, PMI CAPM Prüfungen Ich glaube, alle wissen das, PMI CAPM Prüfungen Wir wachsen gerne mit allen Kandidaten zusammen auf.
Ihm traten fast die Augen aus dem Kopf und sein Gesicht wurde dunkelrot, CAPM Prüfungen Die Götter mögen gnädig sein, er spricht die Wahrheit, Er kam auf diese Idee, als er in einem Waisenhaus in Kenia arbeitete.
Mittlerweile trat die vertraute Sklavin ganz C_S4CSV_2302 Online Test verstört herein, und sagte zu ihrer Herrin: Gnädige Frau, Mesrur und zwei andereHofbedienten, in Begleitung mehrerer Verschnittenen, SC-900 Prüfungen sind an der Türe, und verlangen im Namen des Kalifen mit euch zu sprechen.
Nemos Metaphysik interpretiert Existenz als Wert, Hier ist CAPM Prüfungen ein Fläschchen, Ich denke, dass ihr Fokus auf kreative Arbeit besonders gut durchdacht ist, Der Architekt konnte nicht unterlassen, die Kapelle sogleich in seinen Plan mit hereinzuziehen C-THR89-2205 Dumps Deutsch und besonders diesen engen Raum als ein Denkmal voriger Zeiten und ihres Geschmacks wiederherzustellen.
CAPM Fragen & Antworten & CAPM Studienführer & CAPM Prüfungsvorbereitung
Wenn er starb, mußte er ersetzt werden; an seine Stelle trat wahrscheinlich 1Z0-909 Lerntipps ein jüngster Sohn, der bis dahin Massenindividuum gewesen war wie ein anderer, Ja, er tut mir leid, sehr leid, mein Kind!
Würde es dir etwas ausmachen, mich hinzufahren, Der Kaffee ist CAPM Zertifikatsdemo ja vorzüglich sagte Effi, während sie zugleich das Zimmer und seine Einrichtung musterte, Worauf soll ich mich verlassen?
In seinem Schuldbewußtsein durchschaute er CAPM Prüfungen die Lüge des Kaplans vom Weib Bälzis, das ihn verraten haben solle, nicht recht,er erinnerte sich nur halb, daß er selbst CAPM Prüfungen bei der tollen Beichte unter der Wetterlärche etwas vom Bärenanzünden gesagt hatte.
So lag er still und starrte in die Dunkelheit, Dann aber ermunterte die CAPM Tests morgendliche Fahrt ihn ein wenig, die, zwischen dem Gezwitscher der Vögel, durch die wassererfüllten Geleise der Landstraße dahinging.
keine wirkte in die andere, und empfänge von dieser CAPM PDF Testsoftware wechselseitig Einflüsse, so sage ich: daß das Zugleichsein derselben kein Gegenstand einer möglichen Wahrnehmung sein würde, und daß das Dasein CAPM Prüfungen der einen, durch keinen Weg der empirischen Synthesis, auf das Dasein der anderen führen könnte.
CAPM Übungsmaterialien & CAPM realer Test & CAPM Testvorbereitung
Ich habe keine Zeit, meine Worte zu wägen; und da die Hoheit CAPM selbst es ausgesprochen hat, daß hier kein Geheimnis walte, so enthülle ich schonungslos das Antlitz der Dinge.
Was er wohl wissen wollte, Das werden wir riskieren, Sibyll sagte CAPM Prüfungen Professor McGo- nagall ungeduldig, Wir gehen davon aus, dass Portfoliokarrieren in den kommenden Jahren noch häufiger werden.
Die Sahnebonbons hatten ihnen höllisch Durst gemacht und sie hatten nichts zu CAPM Online Prüfungen trinken dabei, Halt du den Mund, wenn sich Erwachsene unterhalten, Zeus verwandelte sich in goldenen Regen in den Turm und sie wurde Mutter des Perseus.
Ihr schrubbt Euch noch die Haut vom Fleisch, Er wird ent- lassen, wenn der Spuk CAPM Zertifizierungsantworten nicht bald aufhört, Ich grinste, als ich die gute Nachricht verkündete, Oh und den Fuß vom Boden zu heben vermochtest du nicht, und alle Qualen zu enden!
Oh, vergiss es sagte der kleine Mann, Dies CAPM Prüfungen ist ein weiteres Beispiel für das, was wir uns als Yin und Yang der Arbeit inder New Economy vorstellen, Wir haben ungefähr CAPM Prüfungen während des Testens verbracht und etwas jenseits des Engagements generiert.
Es gibt auch eine hässliche Seite der Reziprozität: die Vergeltung.
NEW QUESTION: 1
In which four clauses can a sub query be used? (Choose four.)
A. in the SET clause of an UPDATE statement
B. in the GROUP BY clause of a SELECT statement
C. in the VALUES clause of an INSERT statement
D. in the WHERE clause of a SELECT statement
E. in the FROM clause of a SELECT statement
F. in the INTO clause of an INSERT statement
Answer: A,D,E,F
Explanation:
Explanation/Reference:
Explanation:
A: a sub query is valid on the INTO clause of an ISERT Statement
B: a sub query can be used in the FROM clause of a SELECT statement
D: a sub query can be used in the WHERE clause of a SELECT statement,
E: a sub query can be used in the SET clauses of an UPDATE statement,
Incorrect answer:
Csub query cannot be used
F: is incorrect.
Refer: Introduction to Oracle9i: SQL, Oracle University Study Guide, 6-5
NEW QUESTION: 2
When the NLRA imposes a voluntary-recognition bar, this means what?
A. The NLRB has certified a bargaining representative.
B. The union withdrew its petition for an election.
C. A representation election took place in the previous 12 months.
D. No election will take place for a reasonable period of time.
Answer: D
Explanation:
Answer option C is correct.The NLRB imposes a voluntary-recognition bar while negotiations take place between the union and an employer that voluntarily recognized the union. See Chapter 7 for more information. Chapter: Employee and Labor Relations Objective: Labor Relations
NEW QUESTION: 3
For IBM Case Manager, where should the database for the content engine target object store and the process engine on DB2 be located?
A. On the same database on a server with different userids
B. On separate databases on the same server
C. On the same database on a server with same userid and password
D. On separate databases on different servers
Answer: C
Since this is only a probability it does not need an immediate action. Just try to gather more information as the project goes ahead and decide later on. | |
As a seasoned construction project manager, contact the regulatory body to find out some workarounds for your project. | |
This requires a scope change notification that should be written immediately. | |
Your first and immediate action is to disclose your discovery to the project stakeholders and solicit their viewpoints. |
Question 2 |
40 | |
100 | |
45 | |
90 |
n(n − 1)/2, where n is the number of stakeholders including yourself.
In your project, 10(10 − 1)/2 = 45.
Question 3 |
Stick to your original schedule and tell the customer that once the contract is signed the project duration won’t change under any circumstances. | |
Accept the customer’s request and cut parts of the project scope to meet the new deadline. | |
Inform the customer of the impacts of his requirement to project constraints and, after getting the required approvals, crash the project. | |
Cut the duration of all project activities across the board to meet the requirement. |
Question 4 |
Confront the person about his behavior and its impact on the project. Also, inform the customer about the issue. | |
Ask the customer to replace the person. | |
Since the person is assigned by your client you don’t have any authority over him, so don’t do anything. | |
You unilaterally decide to isolate the person and don’t let him in the project meetings. |
Question 5 |
Precedence Diagramming | |
Activity-On-Arrows Diagramming | |
Leads and Lags | |
Critical Diagramming |
Question 6 |
Start-to-Finish | |
Finish-to-Finish | |
Start-to-Start | |
Finish-to-Start |
Question 7 |
Business Case | |
Project Charter | |
Project Contract | |
Project Statement of Work (SOW) |
Question 8 |
It’s suggested to handle conflicts in the team meetings so that everybody in the project team learns from them. | |
Conflicts are harmful to the project's progress, therefore you need to smooth them when they happen. | |
The best approach is to address the conflicts immediately and in a direct way involving both members, but preferably in private. | |
The best approach is to ignore conflicts because they are common and unavoidable in all of the projects. |
Question 9 |
Risk Register | |
Risk Mitigation Plan | |
Contingency Plan | |
Risk Profile |
Question 10 |
Describes the details of each component in the project WBS | |
Used as a glossary to define the acronyms used in the project WBS | |
It is used for the planning of the project resources | |
Used as a glossary to define the acronyms used in the project scope statement |
Question 11 |
Claims Administration | |
Negotiation | |
Inspection | |
Audits |
Question 12 |
Communication Matrix | |
One-on-One discussion | |
Bidder Conferences | |
Formal Presentation |
Question 13 |
- Actual Cost: $2,000,000
- Cost Variance: $-200,000
- SPI: 1.1
- Budget at Completion (BaC): $5,200,000
$5,200,000 | |
$1,800,000 | |
$3,200,000 | |
$2,200,000 |
−200,000 = EV − 2,000,000
EV = 1,800,000
Question 14 |
The project is getting 87 cents out of each dollar spent. | |
Your project is running according to the budget. | |
The progress of your project is only 87% of what it is planned, so you are behind the schedule. | |
You are ahead of schedule. |
Question 15 |
Project Resources Matrix (PRM) | |
Project Schedule | |
Resource Planning Chart (RPC) | |
Responsibility Assignment Matrix (RAM) |
Question 16 |
Indirect and direct costs | |
Direct and variable costs | |
Indirect and variable costs | |
Variable and fixed costs |
Question 17 |
Planning | |
Executing | |
Monitoring & Controlling | |
Initiating |
Question 18 |
Release the Project Team | |
Perform Procurement Audits | |
Perform Inspections & Audits | |
Refer to Project Closure Guidelines in Organizational Process Assets |
Question 19 |
Inspection | |
Facilitation | |
Prototypes | |
Questionnaires & Surveys |
Question 20 |
Finish-to-start with a 15-day lag | |
Finish-to-finish with a 15-day lag | |
Start-to-finish with a 15-day lead | |
Finish-to-start with a 15-day lead |
Question 21 |
Norming | |
Delegating | |
Forming | |
Performing |
Question 22 |
- Earned Value = $500,000
- Actual Cost = $550,000
- Planned Value = $600,000
Behind schedule and under budget | |
Ahead of schedule and over budget | |
Ahead of schedule and under budget | |
Behind schedule and over budget |
SV = 500,000 − 600,000
SV = $−100,000
Since SV is negative the project is behind schedule.
CV = EV − AC
CV = 500,000 − 550,000
CV = $−50,000
Since CV is negative the project is over budget.
Question 23 |
Staffing Management Plan | |
Organizational chart | |
RAM | |
Project team assignments |
Question 24 |
Stakeholders Register | |
Organizational Process Assets | |
Agreements | |
Business Case |
- Business Case
- Agreements
- Enterprise Environmental Factors
- Organizational Process Assets
Question 25 |
Deliverables | |
Change Requests | |
Work Performance Reports | |
Project document updates |
- Deliverables
- Work Performance data
- Issue log
- Change requests
- Project management plan updates
- Project document updates
- Organizational process assets updates
Question 26 |
Mutual agreement of both parties to terminate | |
Cause or convenience outside the terminations clause of the contract | |
Convenience of the buyer provided in the contract | |
Default of one party |
Question 27 |
Estimate costs | |
Develop schedule | |
Monitor & control project work | |
Determine budget |
Question 28 |
The critical path has zero total float and it shows the earliest possible time to complete the project | |
The critical path consumes the biggest portion of the project budget compared to other paths | |
A project can have only one critical path | |
The critical path has zero or negative total float |
Question 29 |
Virtual Teams | |
Multicriteria Decision Analysis | |
Pre-Assignment | |
Negotiation |
Question 30 |
Rolling wave planning | |
Agile planning | |
Progressive planning | |
Water fall planning |
Question 31 |

Task A | |
Tasks C & E | |
Tasks D & E & F | |
Tasks B & D |
Task A = 6,500
Tasks C & E = 2,000 + 3,500 = 5,500
Tasks B & D = 2,500 + 3,500 = 6,000
Tasks D & E & F = 3,500 + 3,500 + 4,000 = 11,000
Question 32 |
Perform the changes according to the manager’s request because they are crucial to the project success, but document them later on when the project is on track and there are no more changes to be made. | |
Since what the manager has asked you is unethical you should refuse the changes. | |
Explain to the manager that the change should be handled through the formal change management process and it should be documented. | |
Comply with the manager’s request since it is critical to the project success. |
Question 33 |
Control Quality | |
Plan Risk Response | |
Identify Risk | |
Perform Qualitative Risk Analysis |
Question 34 |
Measuring the project scope against the project management plan. | |
Finalizing all activities across all of the Project Management Process Groups. | |
If a project is terminated before completion, starting procedures to investigate and document the reasons for this early termination. | |
Performing activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use. |
Question 35 |
Mitigate | |
Accept | |
Exploit | |
Transfer |
Question 36 |
Project Risk Register | |
Project Charter | |
Issue Log | |
Project Management Plan |
Question 37 |
Raise the issue to higher level managers who can decide on project priorities | |
Negotiate with the functional manager | |
Change the sequence of activities so that he can cope with the resource limitations | |
Record this as a risk in the risk register |
Question 38 |
Analyze the impacts of the change | |
Update the project risk register | |
Issue a Change Request | |
Raise the issue to the project sponsor |
Question 39 |
A more accurate risk response planning | |
A clearer communication management plan | |
A better project management plan | |
A more accurate stakeholder identification |
Question 40 |
Quality measures | |
Rework | |
Downtime | |
Warranty |
Question 41 |
Stakeholder cube | |
Salience model | |
Stakeholder engagement assessment matrix (SEAM) | |
Power/Interest grid |
Question 42 |
−19% | |
−16% | |
19% | |
16% |
SV% = ($470,000 − $560,000) / $560,000
SV% = −16%
Question 43 |
Strategies for negative risks or threats | |
Strategies for positive risks or opportunities | |
Contingent response strategies | |
Risk Reassessment |
Question 44 |
$63,333 | |
$20,000 | |
−$20,000 | |
−$63,333 |
Earn Value = (Total Cost / Total Project Months) * Total Months Completed
Earn Value = ($1,000,000 / 12) * 5
Earn Value = 416,667
CV = 416,667 − $480,000
CV = −$63,333.
Question 45 |
Establishing Ground Rules | |
Training | |
Co-Location | |
Team-building activities |
Question 46 |
Perform claim administration | |
Raise the risk to the Sponsor | |
Initiate a change request | |
Perform inspection & audit |
Question 47 |
Indirect costs | |
Sunk Costs | |
Fixed Costs | |
Variable Costs |
Question 48 |
Project management plans | |
Gantt Charts | |
Milestone reports | |
Project detailed schedules |
List |